District Master Plan - Construction Updates

Multi-Purpose Room Renovation


 

Week of August 10th – August 14th

  • AFP Specialties removed sprinkler heads and lines in mechanical room 307.
  • Bay Area Demolition continued removing sections of the existing stairs and shaft. Erected temporary shoring around existing stair shaft.
  • Bay Area Demolition continued cutting and removing block for new window openings.
  • Bay Area Demolition cut the second floor opening for the new stair shaft.
  • Berger & King continued mechanical demolition in mechanical room 307 and 308.
  • Beger & King installed a 3” water line.
  • Berger & King Removed sanitary line in the shooting range.
  • Drillworks installed one test micropile.
  • Moore Trosper began patching existing floor penetrations.
  • Shoreline Power Services ran conduit on the second floor and installed temporary power in the Multi-Purpose room.

 


Week of August 17th – August 21st

 

  • Bay Area Demolition cut the first floor opening for the new stair shaft.
  • Bay Area Demolition began removing block for multipurpose room entry doors and door 184B. Removed ceiling in corridor adjacent to the multi-purpose room.
  • Bay Are Demolition removed door and frame from pool room office.
  • Bay Area Demolition removed flooring in corridor 106.
  • Berger & King continued mechanical demolition in mechanical room 308. Installed hot water supply and return piping.
  • Bell Masonry continued working on pool infill walls.
  • Bell Masonry began toothing in windows in the multipurpose room.
  • Drillworks began installing micropiles.
  • L&L Contracting began framing second floor walls.
  • Moore Trosper continued patching existing floor penetrations.
  • Northwoods Products delivered lintels, bearing plates, and structural steel.
  • Shoreline Power Services installed conduit on the second floor and multi-purpose room.
  • Quality Environmental Services performed asbestos abatement in mechanical room 307.

 

 


Week of August 24th – August 28th

  • Bay Area Demolition cut and removed concrete for new basement door 011.
  • Bay Area Demolition removed steel backstop from shooting range.
  • Bay Area Demolition removed some ceiling in the basement for the new basement walls.
  • Bay Area Demolition trimmed steel and precast floor openings for new stairs.
  • Bay Area Demolition removed existing batting cage nets and support steel.
  • Berger & King continued mechanical demolition in mechanical room 307.
  • Berger & King cored holes and installed pipe hangers on the second floor.
  • Berger & King installed 2” and 3” hot water supply and return lines in mechanical room 307. Continued running water lines in the locker rooms. Insulated completed water lines on the second floor.
  • Bell Masonry continued toothing in new window openings.
  • Drillworks continued and completed installing micropilles for the new stair and elevator shafts.
  • L&L Contracting continued framing second floor walls.
  • Began hanging drywall.
  • Moore Trosper constructed firewall enclosure around new multi-purpose room windows.
  • Shoreline Power Services continued installing conduit on the second floor.

 

 


Week of August 31st – September 4th

  • Bay Area Demolition removed a section of the existing multi-purpose room ceiling.
  • Berger & King investigated existing sump pump to ensure it is operating correctly.
  • Berger & King ran 2” and 3” hot water supply and return lines across the multi-purpose room.
  • Berger & King demoed piping in the multi-purpose room.
  • Berger & King installed new sump pump.
  • Bell Masonry continued toothing in new window openings and setting lintels.
  • L&L Contracting continued framing and hanging drywall for second floor walls. Began insulating walls and taping hung drywall.
  • Moore Trosper installed additional safety railings.
  • Drillworks demobilized from the site.
  • Shoreline Power Services installed conduit in the locker room corridor.
  • Shoreline Power Services continued installing conduit on the second floor.

 

 


Week of September 7th – September 10th

 

  • Berger & King continued duct demo in Mechanical Room 307 and continued installing hot water supply/return lines in the Multi-Purpose Room.
  • Bell Masonry grouted the cores of pool infill walls and set the structural steel bearing plates. Also toothed in corridor wall near door 184B and laid block up to door frame 18A.
  • L&L Contracting continued working on second floor smoke/fire walls.
  • Shoreline Power Services continued running conduit in the basement.

 

 

 

Sault Area Public Schools Celebrates Grand Opening of "Reaching for the Stars" Playground

"The 'spinny thing' was a fun part of the playground. I can't wait to play on it with my new friends at school!" 
Fiona Skog, age 7, entering 2nd grade at SAES.

SAULT STE. MARIE, MI | August 20, 2026 

A packed multipurpose room filled with children, parents, teachers, staff, community members, city officials, and school leaders gathered Wednesday afternoon to celebrate the official opening and dedication of the new "Reaching for the Stars" Playground at Sault Area Elementary School. 


     The ceremony marked the completion of a community-driven project designed to promote childhood wellness, creativity, connection, and learning through play. The event featured a live broadcast by Mark San Angelo of Rock 101, a military-connected student-led Pledge of Allegiance, a ceremonial drum by Bud Biron, a smudging ceremony conducted by Native American Advisor Tyler Bouschor, and the release of ceremonial doves by Emily Hastings. 
Superintendent Dr. Amy Kronemeyer welcomed attendees and reflected on the collaborative process that led to the playground's "Reaching for the Stars" theme. 
     "Last year, members of the Sault Community Coalition met with playground designer Doug Penchura to begin envisioning a new play space for our children," said Kronemeyer. "Rather than deciding ourselves, we challenged our students to share their hopes and dreams through writing and drawing. Their ideas inspired the design, and through a schoolwide vote, the vision for this playground became a reality." 
     The playground was made possible through the generosity of the Sault community following the successful passage of the August 5, 2025 school millage. District leaders expressed gratitude for the community's continued investment in local children and families. 
     "This playground is far more than equipment," Kronemeyer said. "It is a reflection of what is possible when a community comes together around its children. Every child deserves opportunities to explore, imagine, build friendships, and experience the joy of play. We are grateful to everyone who helped bring this dream to life." 
Kronemeyer emphasized that the playground reflects the district's belief that play is an essential part of learning and healthy child development. 
     "Play is not a break from learning. Play is how children learn best," she said. "This space celebrates childhood wellness while fostering the confidence, curiosity, creativity, and social connections that support lifelong learning." 
The district recognized the many partners whose expertise, creativity, and commitment helped bring the project together, including: 

  • Doug Penchura, Playground Designer

  • Landscape Structures, Equipment Engineers

  • Ken Carlson LLC, Playground Installer and Future Fencing Contractor

  • ForeverLawn, Turf Design and Installation Partner


     Board of Education Trustee Melissa Pingatore shared her appreciation for the day and the impact the playground will have on local children. 
     "It brought me great joy to watch the ceremony and to see so many children run and play," said Pingatore. "Moments like this remind us why investing in our kids matters. This playground will create memories, friendships, and opportunities for children for many years to come." 
     Principal Carl McCready was joined for the ribbon-cutting ceremony by four members of the Class of 2039: Jack Dobrowolski, Silas McComas, Laurel Pierce, and Isla Wagner. Together with other Sault children, they counted down and officially opened the playground. 
     As the ribbon was cut, DJ Mark turned up the music and children eagerly rushed into the new play area to explore the equipment for the first time. Laughter echoed across the playground as families watched children test climbing structures, slides, swings, and, as Fiona enthusiastically noted, the popular "spinny thing." 
     “The new playground is a wonderful addition to the elementary school.  A huge thank you to our community for making it possible. I had the best seat in the house seeing the joy in our students' faces as they were allowed to run and play on the structure for the first time.” Principal McCready stated.

     The playground was formally dedicated to the children of the Sault community in recognition of a shared commitment to childhood wellness, healthy development, and inspiring a love of learning through play. 

For additional information, contact Principal Carl McCready.
 

Multi-Purpose Room Renovation


 


Week of July 6th – July 10th

  • Bay Area Demolition began removing block walls, doors/frames, tile, and plaster ceilings from the locker rooms.
  • Bay Area Demolition continued removing pool tile.
  • Bell Masonry installed formwork and rebar for the pool footings.
  • Berger & King continued mechanical/plumbing demolition on the second floor.
  • Shoreline Power Services continued electrical demolition. Removed circuits from panel in corridor 106 and mechanical room 307.
  • Otwell Mawby visited the site to conduct further asbestos investigation.

 

 

 


Week of July 13th – July 17th 

  • Bay Area Demolition continued locker room demolition and removing pool tile.
  • Bay Area Demolition began removing block walls on the second floor.
  • Bell Masonry poured the concrete pool footings and installed steel angle on pool walls. Also stripped footing forms.
  • Bell Masonry staged masonry in preparation to lay pool infill walls. Began laying block in the pool.
  • Berger & King installed hangers in corridor 106
  • Berger & King removed piping from locker room walls that were demoed.
  • Shoreline Power Services continued electrical and fire alarm demolition. Tracing/Removing circuits.

 

 


Week of July 20th – July 24th

  • Bay Area Demolition installed temporary shoring under the first floor
  • Bay Area Demolition continued locker room demo.
  • Berger & King staged duct deliveries in the basement, continued mechanical demo on the second floor, and cored holes through existing walls for water lines.
  • Berger & King installed duct in the basement, removed existing water lines, and installed waterline to mechanical room 308.
  • Shoreline Power Services continued fire alarm and electrical demo.

 

 


Week of July 27th  – July 31st

  • Bay Area Demolition began removing concrete from stair pans and stair sections/landings, began removing the pool gutter, and continued removing pool tile.
  • Bay Area Demolition installed dust control measures in school corridor for new multi-purpose room windows. Began cutting block for the windows.
  • Bay Area Demo removed pool scoreboard and banners.
  • Bay Area Demolition cut new window opening on the second floor.

 

  • Berger & King continued installing duct in the basement.
  • Berger & King continued plumbing demolition in the locker rooms.

  • Berger & King installed pipe hangers in the locker room.
  • Bell Masonry laid the masonry infill walls in the pool.
  • Shoreline Power Services investigated parking lot light wiring and performed a repair. Also installed conduit through the roof.

 

 


Week of August 3rd  – August 6th

  • Bay Area Demolition continued the stair shaft demo.
  • Bay Area Demolition removed pool diving board.
  • Berger & King continued installing water lines in the locker rooms.
  • Berger & King began mechanical demolition in mech room 307.
  • Shoreline Power Services continued installing temporary power on the second floor.

 

 

 

Multi-Purpose Room Renovation


 

 


Week of June 1st – June 5th

  • Spence Brothers mobilized to the site
  • SB captured photos of existing conditions
  • SB completed measurements for temporary fencing and planned locations for site construction laydown

 

 

 


Week of June 8th – June 12th 

  • Berger & King began demoing the existing mechanical ductwork in the basement
  • Berger & King began shutting off water valves and draining the plumbing piping
  • Spence Brothers site trailer was delivered
  • Shoreline Electric tied the site trailer into temporary power
  • Shoreline Electric investigated parking lot lighting wiring that was struck during the soil boring
  • SSMAPS Construction kickoff meeting was held on Thursday, 6/11.

 

 


Week of June 15th – June 19th

  • Berger & King began removing toilets, sinks, and urinals from the locker rooms
  • Berger & King continued demoing existing mechanical ductwork in the basement and began removing plumbing piping
  • Shoreline installed temporary lighting in the basement
  • SSMAPS removed bleachers from the pool area, benches from the locker rooms, and other miscellaneous school belongings
  • Temporary construction fencing was installed
  • Spence Brothers reworked temporary fencing east & west of the tennis courts

 

 


Week of June 22nd  – June 26th

  • Bay Area Demolition began removing lockers
  • Bay Area Demolition installed temporary construction ramp
  • Bay Area Demolition cut temporary lintels into the exterior wall for door opening 302C
  • Bay Area Demolition removed block & brick for door opening 302C
  • Bay Area Demolition disassembled 2nd floor bleachers
  • Bay Area Demolition removed tile from pool
  • Berger & King continued demoing the mechanical ductwork and plumbing piping
  • Berger & King shutoff the gas to cut & cap the gas lines serving the locker rooms

 

  • Bell Masonry laid out the foundations in the pool for tile removal
  • Moore Trosper removed the existing steel bars at door 184D and installed temporary doors at this opening
  • Moore Trosper installed temporary safety railings around the pool and door opening 302C.
  • Shoreline Electric raised the temporary power lines for the site trailer
  • Shoreline Electric continued installing temporary lighting
  • Quality Environmental performed asbestos abatement; removed the floor tiles from the basement, removed the fire doors, and the mechanical duct vibration dampeners
  • MIOSHA visited the site for a safety walk

 

 


Week of June 29th  – July 2nd

  • Bay Area Demolition continued removing lockers and demoing pool tile
  • Bay Area Demolition removed the ceiling in the existing cheer/dance room and removed the batting cages
  • Bay Area Demolition disassembled pool judging platform and stored it outside near the bleachers
  • Bay Area Demolition installed duct control measures on the 2nd floor
  • Bell Masonry installed forms for the pool footings
  • Bell Masonry installed crushed stone in the deep end of the pool
  • Berger & King Removing drain lines from the pool
  • Berger & King removed duct near the pool pumps and began the locker room duct demo.

 

  • Berger & King removed wall heaters
  • Moore Trosper reworked existing tennis court fencing
  • Shoreline began reworking the existing fire alarm system
  • Shoreline began removing wiring from the mezzanine walls for wall demolition
  • Shoreline removed electrical components from wall heaters. They also began tracking down circuits from panel EB and removed all circuits that can be removed.
  • AFP Specialties visited the site to prepare for sprinkler line demolition

 

 

 

June 2026


Sault Schools Construction & Community Update

Sault Schools continues to make strong progress on several construction and facility projects that directly support student learning and strengthen our broader community. These efforts reflect the vision shared during our bond campaign and our ongoing commitment to creating high-quality, future-ready spaces. 


Elementary Updates

School Roof

Work on the Elementary School roof is actively underway and progressing on schedule. This important upgrade will improve the long-term durability of the building, enhance energy efficiency, and ensure a safe, comfortable learning environment for our students. 

Classrooms for grades 2–5 will receive a fresh update over the next month, including new paint and flooring to create bright, welcoming learning spaces.

 

 

 

 

 


Sault Secondary Transformation

We are proud to share that construction bids totaling $9.6 million have been officially awarded. The next phase of demolition and construction is scheduled to begin on June 9, moving this project from preparation into active status followed by rebuilding and renovation. 

This investment represents a major milestone in creating modern, engaging spaces that better serve both students and staff. 


Playground Improvements

Site work has begun for the new playground at Soo Township. Early construction efforts are focused on site preparation, setting the stage for a safe, inclusive, and engaging outdoor space that supports both play and learning. 

The Sault Elementary playground will follow in late June.


Washington and Lincoln: Community-Focused Repurposing

The Washington and Lincoln buildings are being thoughtfully repurposed for the betterment of our community—fulfilling a key promise made during the bond campaign. 

These facilities represent an important opportunity to expand our Community vision by supporting partnerships, programming, and services that benefit the greater Sault area. Planning efforts are ongoing, and we look forward to sharing more details as these spaces evolve to meet community needs. 


Moving Forward Together

We are grateful for the continued support of our community as these important projects move forward. Each step reflects our shared commitment to providing exceptional learning environments while strengthening the connections that make Sault Schools a vital part of this community.